CASE STUDY · POWER
33 kV UG Cable 300 sq.mm — Latur
Supply and laying of 33 kV underground XLPE cable network with terminations and joints.

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33 kV UG Cable 300 sq.mm

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
Site progress

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
Commissioning
PROJECT SPECIFICATIONS
VOLTAGE
33 kV
CABLE SIZE
3C × 300 sq.mm XLPE
JOINTS
Heat-shrink straight-through
TERMINATIONS
Outdoor heat-shrink
STATUS
COMMISSIONED
Scope of work
What we executed.
- Route survey, trenching and sand bedding
- Cable pulling with calibrated tension limits
- Straight-through joints and outdoor terminations
- Insulation, HV and sheath tests pre-energization
- Cable route marker installation and as-built records
Execution notes
From site, in plain terms.
Joints made in dry tent conditions per cable maker's procedure.
All terminations tested with 5 kV motorised insulation tester before charging.
From site
Photo gallery.

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33 kV UG Cable 300 sq.mm · Frame 1

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33 kV UG Cable 300 sq.mm · Frame 2

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33 kV UG Cable 300 sq.mm · Frame 3

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33 kV UG Cable 300 sq.mm · Frame 4

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33 kV UG Cable 300 sq.mm · Frame 5

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33 kV UG Cable 300 sq.mm · Frame 6
Outcome
Cable network energized and handed over to MSEDCL Latur sub-division.
Related case studies
More from this sector.

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
33/11 kV Substation
18.4088°N · 76.5604°ELATUR · MAHARASHTRA
33/11 kV Substation — Latur
MSEDCL · Power · 2023

18.2877°N · 74.0084°E
PURANDAR · MAHARASHTRA
6.3 MVA Power Transformer
18.2877°N · 74.0084°EPURANDAR · MAHARASHTRA
6.3 MVA Power Transformer — Purandar
MSEDCL · Power · 2024

18.4088°N · 76.5604°E
LATUR · MAHARASHTRA
11 kV UG Cable Network
18.4088°N · 76.5604°ELATUR · MAHARASHTRA
11 kV UG Cable Network — Latur
MSEDCL · Power · 2020
Speak to our team.
Tender evaluation, vendor enquiry or a site visit — we respond within one working day.